    Hello,
    how do i start an advanced multi-row queue sequence with a scheduled task?

    Thanks in advance.

    Rgds

    #14209
    doug
    Moderator

    Two options:

    1. Direct Task Scheduler: In the Task Scheduler select the drop-town Task as Execute advanced multi-row queue sequence. The row where you set this task must be the Execution Row for the desired advanced multi-row queue sequence.

    2. Via the Job Queue: Create and save a job queue that uses the special item Execute advanced multi-row sequence:X. Then create a scheduled task that launches the job queue that you created.