Advanced multi-row queue sequence with Scheduled task

BatchPatch Forums Home Forums BatchPatch Support Forum Advanced multi-row queue sequence with Scheduled task

  • This topic has 1 reply, 2 voices, and was last updated 9 months ago by doug.
Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #14207
    DSK
    Participant

    Hello,
    how do i start an advanced multi-row queue sequence with a scheduled task?

    Thanks in advance.

    Rgds

    #14209
    doug
    Moderator

    Two options:

    1. Direct Task Scheduler: In the Task Scheduler select the drop-town Task as Execute advanced multi-row queue sequence. The row where you set this task must be the Execution Row for the desired advanced multi-row queue sequence.

    2. Via the Job Queue: Create and save a job queue that uses the special item Execute advanced multi-row sequence:X. Then create a scheduled task that launches the job queue that you created.

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.